Feasibility Study for Tripoli Sewerage System
and Waste Water Treatment Plant
Sour and Kfarhilda Treatment Plants

Feasibility Study for Tripoli Sewerage System
and Wastewater Treatment Plant

Location Tripoli - Lebanon
Client Ministry of Hydraulic and Electric Resources and Council for Development and Reconstruction
Duration of Services 1995 - 1997 (15 months)
Cost of Implementation

USD 100 Million
Phase 1

Financing of Works European Bank for Investment (EIB)
 
Project Main Components and Features
Master Plan for sewage collection networks
Master Plan for storm water drainage systems
Wastewater treatment plant - Secondary treatment
Sea outfall 2.6km long

Average effluent quality:
30mg/L BOD5
30 mg/L SS

Sewage treatment plant:
Ultimate average and peak quantities of domestic and industrial discharges as well as infiltration and other flows reaching the wastewater treatment plant will be 3.3 m3/s (1,740,000 PE) and 4.92 m3/s.

The adopted discharge values are 60 g/c/d of BOD5 and 70 g/c/d of suspended solids.
  The main units of the wastewater treatment plant including sludge treatment facilities are as follows:

• Screens
• Aerated grit/grease chambers
• Primary sedimentation tanks
• Aeration tanks
• Secondary (or final) sedimentation tanks
• Return activated sludge pumping station
• Raw sludge thickeners
• Digestion tanks
• Gas storage tank
• Digested sludge thickeners / holding tanks
• Sludge conditioning
• Sludge dewatering unit
• Odour control system
• Disinfection unit (only in case the final effluent is to be used for irrigation)
• Final effluent pumping station

Scope of Services
Feasibility Study for sewage networks
and drainage systems
Preparation of a Master Plan for wastewater
and storm water collection systems
Preaparation of Tender Documents for sewage treatment plant and sea outfall